Our work spans the entire province of Quebec, from Abitibi to the Côte-Nord. Each project reflects our bridge expertise, tailored to the unique challenges of every region.
The bridge was rebuilt from 80' to 120' to improve water flow. The work was carried out during the winter. The new structure includes a central pier, which clears the riverbanks on both sides and facilitates better water movement.
The original culvert was regularly blocked by debris, compromising access and user safety. Replacing it with a 45' bridge eliminated the issue and significantly improved infrastructure durability.
This 70' bridge was rebuilt under winter conditions. Construction was adapted to ensure the structure’s stability and efficiency despite seasonal constraints.
Challenging soil conditions required a custom design. A 70' steel-wood bridge—lighter than a concrete abutment structure—was selected. Carefully prepared sub-foundations ensured stability while generating significant time and cost savings.